Technique study about toe slab built on thick overburden layer of concrete face dam

ZHENG Yi-fang,JIN Wei
DOI: https://doi.org/10.3969/j.issn.1002-0624.2013.09.002
2013-01-01
Abstract:As a new type of the earth-rock dam,the reinforced concrete face rock-fill dam has the advantages of reducing the dam section,saving project cost,shorting the construction period and simplifying the construction diversion.The paper introduces the recent development status of concrete face rock-fill dam with the toe slab built on thick overburden layer at home and abroad,summarizes some key techniques for the design of the dam type,which has the reference for the design and calculation of concrete face rock-fill dam on thick overburden.