Study on the Model Tests of Jiujinggang Hydropower Station

Liang Hanhua,Fu Jingyao,Wang Zhenyu
DOI: https://doi.org/10.3969/j.issn.0559-9342.2006.07.029
2006-01-01
Abstract:This paper examines the project of the model tests,as well as its testing methods,of Jiujinggang Hydropower Station.Through these tests,the discharging ability of the spillway is computed.The wall height of the overflow groove is validated,and the probability of cavitation erosion is also analyzed.An optimized arrangement project of the spillway and suggestions of structural measures to the riversides are proposed.This paper may present as a reference in other engineering designs and model tests as well.
What problem does this paper attempt to address?