System Study for a Tens MWe Size Coal—Fired MHD Retrofit Pilot Power Plant in China

Ningsheng Cai,Yiqian Xu,James N. Chapman,Ciwen Sha
DOI: https://doi.org/10.1007/bf02650840
1993-01-01
Abstract:System analysis is made in this paper of the coal-fired MHD/steam combined cycle pilot power plant in the size range tens of MWe. System performance are presented of such plants with three sizes: one 12 MWe unit, two 12 MWe units and one 50 MWe unit which are considered as retrofits to the existing Beijing No.3 Heat and Power Plant. Parametric studies are performed for the 2 × 12 MWe units and the optimum system parameters are obtained.