Abstract:According to the requirements of DL/T869—2004 thermal power plant welding standards,100% radiation test should be conducted when welding is about 20 mm and 100% ultrasonic test should be conducted when welding is completed for pipelines that are no less than 70 mm thick.This article compares the commonly used testing measures in construction and suggests the proper method to ensure the quality of the welding joints and the inside of the welding parts.