Practical methods of risk estimation for two key construction phases of reclamation from sea

LU Yong-jin,HE You-sheng,LIU Hua
DOI: https://doi.org/10.16483/j.issn.1005-9865.2006.01.007
2006-01-01
Abstract:The closure protection and closing as well as the dike stability control are two key risk-control phases of the engineering of reclamation from the sea.The practical methods for estimating the risk of the two phases is much needed.The limit state function of flow over the closure is given under an assumption of weir flow.The statistic distribution and parameters of the stochastic variables are analyzed.The JC method is recommended to estimate the hydraulic risk of the closure.Two simple practical methods which use only the common engineering geologic survey information and homologous project data are provided with the aim of estimating the risk of dike sliding during construction.
What problem does this paper attempt to address?