The Implementation of Automatic Generate Control in Combined Cycle Units

QIN Lai-feng,FENG Xiao-lu,ZHOU Feng
DOI: https://doi.org/10.3969/j.issn.1009-2889.2007.03.014
2007-01-01
Abstract:This paper introduces the basic control system in a specific Zhejiang gas power plant.It summarizes the problems encountered during AGC operation from communication between the DCS and Mark-V,also the communication between the control center of the grid and the DCS,a load attribution strategy was designed,which including the Sama control figure.According to the analyses of AGC test result,this system enhancing the units to realize AGC function and be put into run on time.