Discussion on Application of MUCT Process in Municipal Wastewater Treatment Plant

Fei-yan ZHANG,Gong-zhe HE,Hong-tao CAO,Zhong-fang LEI,Xiang LIU,Yue-chao WANG,Ting WU
DOI: https://doi.org/10.19853/j.zgjsps.1000-4602.2011.06.015
2011-01-01
Abstract:The design treatment capacity of a municipal wastewater treatment plant(MWTP) in Changzhou City is 20×104 m3/d,with modified UCT(MUCT) process being used and the original design effluent meeting the first level B criteria specified in the Discharge Standard of Pollutants for Municipal Wastewater Treatment Plant(GB 18918-2002).The two year operation dada(from 2008 to 2009) indicate that under the existing operation conditions,the effluent quality from the MWTP is better than the original design first level B standard.The first level A standard-reaching rates of COD,BOD5,SS,NH3-N,TN,and TP are 99.5%,100%,83.2%,99.9%,99.9% and 98.8% respectively in the test period of 731 days.SS control should be emphasized for the MWTP upgrading and reconstruction,and some corresponding suggestions are made.
What problem does this paper attempt to address?