ANALYSIS OF COMPARISON OF CERAMIC FLOOR INSTALLATION PRODUCTIVITY AND WAGE COST BASED ON LABOR COMPOSITION

Dwi Sri Wiyanti,Taufik Dwi Laksono
DOI: https://doi.org/10.29121/ijetmr.v9.i6.2022.1176
2022-06-29
International Journal of Engineering Technologies and Management Research
Abstract:Completion time of construction project that consist of many work items should not exceeds the given time requirement and the cost should not exceeds the planned budget. This study analyzed a work item that is floor ceramic installation by acquiring the comparison of labor productivity and the comparison of wage cost based on different labor compositions. Out of the three (3) studied labor compositions in floor ceramic installation, the composition that consist of 2(two) masons and 2(two) journeymen produces the highest productivity that is 1,73 m2 and based on the productivity the incurred wage cost, composition 2(two) is the cheapest with IDR. 9.046,-/m2.