Long-Term Scheduling of Provincial Power Grid With Rich Hydropower

Rui Cao,Jian-jian Shen,Fu Chen,Chun-Tian Cheng,Jian Wang
DOI: https://doi.org/10.1061/9780784480595.044
2017-05-18
Abstract:Southwest China has experienced a rapid development of hydropower in recent years. In contrast, the power demand growth is very slow in the region. The increasing imbalance between power supply and demand have led to great challenges on the hydropower absorption and operation of provincial power grids with rich hydropower. In this paper, a practical method for long-term scheduling of provincial power grids with rich hydropower is proposed. An optimization model with maximizing the absorption of hydropower is formulated. A coordination strategy, which is capable of minimizing the thermal power generation according to the energy-saving scheduling principle, is employed to increase the absorption of hydropower. The proposed method was implemented on the generation scheduling of Yunnan Power Grid (YNPG), with more than 60GW hydropower capacity and 160 large and middle-sized hydropower plants. The case study presents different simulation results by considering scenarios of inflow and demand. It is demonstrated that our method can obviously increase hydropower absorption. It is effective and practical.
What problem does this paper attempt to address?
The problem that this paper attempts to solve is how to optimize the long - term dispatching of provincial power grids, especially how to increase the absorption of hydropower, in the situation where there are abundant hydropower resources but slow growth in power demand in southwest China. Specifically, the paper proposes an optimization model and a coordination strategy, aiming to maximize the utilization of hydropower and reduce the power generation of thermal power through the principle of energy - saving dispatching, thereby increasing the proportion of hydropower in the power grid. Taking the Yunnan power grid as an example, the paper conducts a case study, shows the simulation results under different water inflow and demand scenarios, and proves the effectiveness and practicality of the proposed method.