Oversight and Efficiency in Public Projects: A Regression Discontinuity Analysis

Eduard Calvo,Ruomeng Cui,Juan Camilo Serpa
DOI: https://doi.org/10.2139/ssrn.2876840
2016-01-01
SSRN Electronic Journal
Abstract:In the U.S., four in ten public infrastructure projects report delays or cost overruns. To tackle this problem, regulators often scrutinize the project contractor’s operations. We investigate the causal effect of government oversight on project efficiency by gleaning 262,857 projects that span seventy-one U.S. federal agencies and 54,739 contractors. Our identification strategy exploits a regulatory bylaw: if a project’s anticipated budget exceeds a threshold value, the contractor’s operations are subject to surveillance from independent procurement officers; otherwise, these operational checks are waived. Using a regression discontinuity design, we find that oversight is obstructive to the project’s operations, especially when the contractor (i) has no prior experience in public projects, (ii) is paid with a fixed-price contract that includes performance-based incentives, and (iii) performs a labor-intensive task. In contrast, oversight is least obstructive — or beneficial — when the contractor (i) is experienced, (ii) is paid with a time-and-materials contract, and (iii) performs a machine-intensive task.
What problem does this paper attempt to address?