A robust scheduling for the multi-mode project scheduling problem with a given deadline under uncertainty of activity duration

Hadi Moradi,Shahram Shadrokh
DOI: https://doi.org/10.1080/00207543.2018.1552371
IF: 9.018
2018-12-06
International Journal of Production Research
Abstract:The problem of this paper deals with the multi-mode project scheduling problem under uncertainty of activity duration where only the renewable resources are taken into account and a given deadline has to be met at the cost of recruiting additional resources. A heuristic algorithm is employed to solve this problem, and to maintain the robustness of the baseline schedule, the concept of critical chain project management (CCPM) is applied in which a new definition to resource buffer is considered. A simulation methodology is used to determine the size and location of resource buffers in the schedules in which three different buffer sizes and three different uncertainty levels are considered. Results and analysis of the simulation outcomes illustrate that resource buffers are useful and should be simulated by the CCPM schedules, as they help to decrease the total duration of the project during implementation and meet the deadline of the project with more assurance.
engineering, manufacturing, industrial,operations research & management science
What problem does this paper attempt to address?