Research on Real-time Control of Construction Progress

Li gang,Zhao peng,Sun Shu-hong
DOI: https://doi.org/10.1088/1755-1315/376/1/012010
2019-11-01
IOP Conference Series: Earth and Environmental Science
Abstract:Abstract combining with the chilong river management project, this paper analyzes the factors that affect the progress and the related methods of the progress control. By compiling the network plan, the free time difference and the total time difference in the construction process are analyzed and calculated. It is determined that the key work of construction is Xiaobo pump station, and the key route is Xiaobo pump station excavation-Xiaobo pump station concrete pouring-Xiaobo pump station backfill, and the construction progress is further optimized and analyzed, and the purpose of shortening the construction period is achieved. It is verified that the reasonable arrangement of construction schedule can achieve the purpose of shortening the construction period without increasing the additional cost.
What problem does this paper attempt to address?