Analysis of Stresses and Displacementfor Roller Compacted Concrete Archdam on a Weak Foundation

Penghui Li
2004-01-01
Abstract:A roller compacted concrete arch dam is over 100m high and the foundation is weak, the deformation and stresses in the arch dam were much larger than normal, especially the abutment displacement downstream. A 30 m long stift pier was added to reinforce the abutment and reduce the deformation. Three-dimensional analyses of the stresses and displacement due to the hydraulic pressure showed that the downstream tensile stresses in the arch dam were reduced by 50% and the deformation was reduced by 20%. The stresses in the foundation near the dam abutment were transmitted mainly through the pier, which enlarged the dam foundation and reduced the sinkage. Since the pier reduces dam span and improves its rigidity, the piers share the load on the dam abutment which reduces the stresses so the deformation is controlled.