Development of Construction Management Software Package for Critical Paths in Substation Reconstruction

Nengling Tai
2011-01-01
Abstract:In order to solve the problem produced by manual calculation of progress control in substation reconstruction,the theories of critical paths calculation in substation reconstruction are analyzed in this paper.A software package ECPM is developed for the critical paths calculation with computer program.And the substation reconstruction progress can be controlled effectively.Through a progress control example in a substation reconstruction,the accuracy of the software package is demonstrated.Result shows that it is effective to apply the software to control the substation reconstruction progress and the efficiency is improved.