A Two-Stage Maintenance-Operation Robust Optimization Model Considering Line Forced Outage

Boyou Jiang,Huating Xu,Chuangxin Guo
DOI: https://doi.org/10.1109/ei252483.2021.9713539
2021-01-01
Abstract:Considering the effect of line forced outage in the power system with wind farms, a two-stage maintenance-operation robust optimization model is proposed. The model aims at minimizing maintenance and operation costs as well as wind curtailment and load shedding while considering wind power and line forced outage uncertainties. Then we use column and constraint generation algorithm to solve the two-stage three-layer problem. The simulation results of IEEE 6-bus and IEEE 39-bus systems show that taking all kinds of uncertainties into consideration can significantly enhance the robustness of power systems to deal with uncertainties.
What problem does this paper attempt to address?