Heuristic Algorithm for Multi-Resource Investment Problem in Project Scheduling

王解法,李世敬,冯祖仁
DOI: https://doi.org/10.3969/j.issn.1000-7180.2003.09.010
2003-01-01
Abstract:We proposed a heuristic algorithm for resource leveling problem in project scheduling.The objective is minimizing costs of resource investments subjective to the prescribed maximum project duration and resource profiles.The heuristic algorithm includes two steps:solving resource -constrained project scheduling problem to evaluate the current resource leveling,and modifying the current resource numbers by adding certain bottleneck resources.The algorithm iterates until the project duration reaches the due time.The bottleneck resources are referred to the lack resources used by the item in critical path that has the maximum ratio of wait time to their lack resources prices.