DESIGN IDEA ABOUT EXTRUSION BLASTING OF MULTI-ARCH BRIDGE

崔晓荣,沈兆武,王平
DOI: https://doi.org/10.3969/j.issn.1006-7051.2004.04.012
2004-01-01
Abstract:When the multi-arch bridge is demolished by blasting method,its piers must be remained so as to use them for construction of a new bridge. In blasting project,the workload of drilling-and-charging must be reduced and the flying rocks controlled but a very complex environment,to avoid the damage of the piers by falling arch beams. For this reason,a new method of extrusion blasting is adopted after analyzing the structure of the bridge. In this paper, the drilling-and-charging parameters and priming circuit for extrusion blasting are discussed in detail and the falling procedure of arch beams is analyzed.
What problem does this paper attempt to address?