Multi-Objective Time-Cost Optimization Using Cobb-Douglas Production Function and Hybrid Genetic Algorithm

Zhigang Shen,Ashkan Hassani,Qian Shi
DOI: https://doi.org/10.3846/13923730.2014.897966
2016-01-01
Journal of Civil Engineering and Management
Abstract:Existing research on construction time-cost tradeoff issues rarely explore the origin of the crashing cost. Crashing cost function was either assumed without much justification, or came from historical data of some real pro­jects. As a result the conclusions of the papers can hardly be used to guide allocations of labor and equipment resources respectively. The authors believe Cobb-Douglas function provides a much-needed piece to modeling the cost functions in the construction time-cost tradeoff problem during the crashing process. We believe this new perspective fills a gap of existing time-cost tradeoff research by considering project duration, labor and equipment cost as parameters of the Cobb- Douglas production function. A case study was presented to show how the proposed framework works. Our conclusion is that introducing Cobb-Douglas function into time-cost tradeoff problem provides us extra capacity to further identify the optimal allocations of labor and equipment resources during crashing.
What problem does this paper attempt to address?