Unit Commitment Based On Frequency Regulating Reserve Constraint Using Dynamic Programming

Dr. T. Govindaraj,T. Archana
Abstract:In dynamic programming-based power scheduling algorithms, thousands of hourly economic dispatches must be performed to consider every possible unit combination over all the stages of the optimization interval. The UC problem is formulated to minimize the total generation cost, while the load demand, reserve requirements, and unit constraints are satisfied. Among the UC constraints, an adequate provision of reserve is important to ensure the security of the power system and essential to bring the system back to acceptable level following the loss of a sizable online unit within seconds. If the unit commitment problem is constrained to observe a minimum system spinning reserve, frequency reserve constrained and an economic dispatch of a combination of units does not comply with this requirement, necessary and sufficient conditions have been established to guarantee that the dispatch of these units will meet the constraint. In this paper, we present necessary and sufficient conditions for the feasibility of unit combinations that can be checked off-line.
Engineering
What problem does this paper attempt to address?