Fuzzy programming based scheduling of steam power system in petrochemical complex

廖祖维,宣吉,荣冈,章建栋
DOI: https://doi.org/10.3785/j.issn.1008-973X.2011.04.006
2011-01-01
Abstract:The process data were hard to obtain in existing scheduling methods for steam power system. A scheduling strategy under uncertainty was proposed to deal with the inaccurate data in steam power system. The inaccurate data was presented by triangular fuzzy number, and a fuzzy scheduling model was established. Then the fuzzy model was shifted to a deterministic mixed integer linear programming (MILP) model by using necessity measures and α-level method. Sensitivity analysis was conducted to identify the effects of the imprecise parameters. An example from a certain petrochemical complex was adopted. Results showed that the power demand was most sensitive in the system.
What problem does this paper attempt to address?