Using EMTP to verify new generators trip-off scheme for a long transmission system based on detailed models

Danzhen Gu,Qian Ai,Chen Chen,Hui Fu,Changyi Li
2005-01-01
WSEAS TRANSACTIONS ON CIRCUITS AND SYSTEMS
Abstract:In southeastern of China, there exists Yangcheng-Huaiyin long transmission system. The trip-off scheme of generators in Yangcheng power plant is very rigorous, albeit Fixed Compensation (FC) has been used to promote transient stability. After decade development, the end-point power gird has been reinforced, so the old scheme should be modified. This paper employs ElectroMagnetic Transients Program (EMTP, ATP version) as a simulation tool to verify the new scheme with field tests parameters and detailed models, and hopes the conclusions can give operators some positive suggestions.
What problem does this paper attempt to address?