Modeling of applying detention tanks to increase drainage capacity for existing sewer system

Tan Qiong,Li Tian,Zhang Jian-pin,Shi Zhen-bao
DOI: https://doi.org/10.13789/j.cnki.wwe1964.2006.09.013
2006-01-01
Abstract:Zhenru is chosen as a typical Shanghai drainage system to study the use of detention tank for flooding control in urban areas. Hydraulic model is used to predict required tank volume if current pipe and pumping station size are maintained. The economic advantage is analyzed as well. Result shows that, when using detention tank of 60m~3/hm~2, the key area of Zhenru drainage system can withstand periods of design storm up from 1 year to 3 years, and over 50% construction investment can be saved. The study can provide reference to other drainage system using detention tank for flooding control.
What problem does this paper attempt to address?