Multi-mode resource-constrained project scheduling problem with multiple shifts and dynamic energy prices
Wuliang Peng Dongmin Yu Fang Xie School of Economics and Management,Yantai University,Yantai,People's Republic of ChinaWuliang Peng received the Ph.D. degree in industrial engineering from Northeastern University in 2008. He is currently a full professor at Yantai University. He has published articles in various journals such as the International Journal of Project Management,the International Journal of Production Research,and Annal of Operations research. He is a reviewer for several international journals. His research interests include project management,project scheduling,and manufacturing Informatization et al.Dongmin Yu received master's degree of business management from Yantai University in 2024. His research interests include project management and technology economics management.Fang Xie received the Ph.D. degree in management science and engineering from Beihang University in 2016. She is currently an associate professor at Yantai University. She has published articles in journals such as applied mathematical modelling and expert systems with applications. Her research interests include project management and scheduling,machine scheduling.
DOI: https://doi.org/10.1080/00207543.2024.2403774
IF: 9.018
2024-09-20
International Journal of Production Research
Abstract:Considering the characteristics of time-of-use tariffs and multi-shifts in real-life project execution scenarios, we present a multi-mode resource-constrained project scheduling problem with multi-shift and time-of-use tariffs (MRCPSP-MS-TOU). The MRCPSP-MS-TOU is a bi-objective scheduling problem that aims to simultaneously minimise both project duration and energy costs. In this problem, renewable resources are the critical equipment that consumes the most energy and can work continuously for multiple shifts. Activities that require critical equipment with high energy consumption are given priority for shifts with lower electricity prices under time-of-use tariffs. We construct a mixed integer linear programming model for the MRCPSP-MS-TOU. For small-scale projects, the ε -constraint method is implemented to solve the MRCPSP-MS-TOU using the Gurobi optimiser. For large-scale projects, this paper develops meta-heuristic algorithms in the framework of the two non-dominated sorting genetic algorithm versions. The MRCPSP-MS-TOU enables manufacturers and the construction industry to schedule projects using time-of-use tariffs and multi-shifts in a more efficient manner since it can control the intensity of energy consumption, reduce project costs, make full use of energy-intensive equipment, and effectively reduce order delivery time.
engineering, manufacturing, industrial,operations research & management science