Analysis and information construction of Nanjing Changjiang Tunnel shield originating working well

Wang Yuan,Liu Songyu
2008-01-01
Abstract:Taking the originating working well engineering of Nanjing Changjiang Tunnel shield as the background,the monitoring technical scheme of deep foundation pit information construction was introduced from the engineering monitoring purpose,section design,project and content and other aspects.The surrounding environment,supporting axial force, underground continuous wall internal force and the monitoring results of deep horizontal displacement were analyzed. Combined with the construction conditions,the relevant conclusions were drawn.The present experience and conclusions can be helpful to the design,construction and research of similar projects.
What problem does this paper attempt to address?