A Solution to Cyclic Scheduling Problem of the Crane in Single Oilcan Fixing Line

Zhou Zhi-li
DOI: https://doi.org/10.3969/j.issn.1001-4098.2007.10.019
2008-01-01
Abstract:As an important resource in repairing the oilcan of train,crane affects directly the productivity of the systems.In this paper,we study cyclic scheduling problem of the crane in single line for fixing oilcan,where products are loaded into the system at one end and unloaded at the other end. The processing time at each workstation is needed.There is no buffer between these stations.Crane is used to move products between the workstations in the line.The objective is to schedule the moves to minimize the production cycle.To solve the problem,we developed a mixed integer linear programming model.Numerical example show the proposed method is effect.
What problem does this paper attempt to address?