Dynamic Programming Algorithm on Two Machines Cross Docking Scheduling with Total Weighted Completion Time

MA Dong-yan,CHEN Feng
DOI: https://doi.org/10.3321/j.issn:1006-2467.2007.05.040
2007-01-01
Abstract:This paper considers the cross docking distribution scheduling problem,with the objective to minimize the total weighted completion times.The vehicles used in the receiving and shipping stages could be considered as machines,and the receiving items and customer demands are the processing jobs with precedence sets restrictions between them.The problem's computational complexity and some characteristics about the optimal solution were given.An efficient backward dynamic programming(DP) was developed.The computational experiments show that the proposed DP algorithm can handle problems up to at least 25 jobs.
What problem does this paper attempt to address?