APPLICATION OF BP NEURAL NETWORK TO BACK ANALYSIS OF FORKED TUNNEL DISPLACEMENT

Xiaoming Yi,CHEN Weizhong,LI Shucai,DAI Yonghao
DOI: https://doi.org/10.3321/j.issn:1000-6915.2006.z2.092
2006-01-01
Abstract:In the construction process of west transportation,the section of Yichang—Enshi along Hurong expressway goes through many high and precipitous mountain areas,which induces many problems seldom or never met before.At the aspect of tunnel construction,to adapt to the varying and complex geological and topographic conditions,the forked tunnel together with double-arch,small-interval tunnel styles have been designed,that is,one entrance of the tunnel is four-driveway with big arch or double arches,and the other is apart double tunnels.Based on site monitoring data of the tunnelt,he back analysis of forked tunnel displacement is well performed by combining the well-known finite difference program FLAC3D with BP neural network,considering the effects of broken and damaged zones.According to the results of engineering practice,it is revealed that this kind of back analysis method is capable to large-scale,complicated and nonlinear tunneling engineering,and is robust and practical enough to well meet the precision requirements of geotechnical engineering.Moreover,the results can be expected to be helpful and meaningful to reconnaissance,design and construction for not only the current studied one but also many similar complex and long tunnels in western China.
What problem does this paper attempt to address?