Stochastic Earned Value Analysis using Monte Carlo Simulation and Statistical Learning Techniques

Fernando Acebes,M Pereda,David Poza,Javier Pajares,Jose M Galan
DOI: https://doi.org/10.1016/j.ijproman.2015.06.012
2024-05-31
Abstract:The aim of this paper is to describe a new an integrated methodology for project control under uncertainty. This proposal is based on Earned Value Methodology and risk analysis and presents several refinements to previous methodologies. More specifically, the approach uses extensive Monte Carlo simulation to obtain information about the expected behavior of the project. This dataset is exploited in several ways using different statistical learning methodologies in a structured fashion. Initially, simulations are used to detect if project deviations are a consequence of the expected variability using Anomaly Detection algorithms. If the project follows this expected variability, probabilities of success in cost and time and expected cost and total duration of the project can be estimated using classification and regression approaches.
Risk Management
What problem does this paper attempt to address?
### Problems the Paper Attempts to Solve This paper aims to describe a new project control method to address the challenges of project management under conditions of uncertainty. Specifically, this method is based on Earned Value Methodology (EVM) and risk analysis, and proposes several improvements over previous methods. #### Main Contributions - **Monte Carlo Simulation**: Utilizes extensive Monte Carlo simulations to gather information about the expected behavior of the project. - **Statistical Learning Techniques**: Structurally utilizes this data through various statistical learning methods. - **Anomaly Detection Algorithms**: Used to detect whether project deviations fall within the expected range of variation. - **Classification and Regression Methods**: If the project falls within the expected range of variation, the probability of success in terms of cost and time, as well as the expected cost and total duration, can be estimated. #### Key Techniques - **Anomaly Detection Algorithms**: Used to identify anomalies in the project, distinguishing between random fluctuations and structural issues. - **Classification Problems**: Predicts whether the project will be completed on time or within budget using classification algorithms and provides the corresponding probabilities. - **Regression Problems**: Predicts the final cost and time of the project. Through these techniques, project managers can better understand the state of the project and take appropriate corrective actions.