Stochastic Earned Duration Analysis for Project Schedule Management

Fernando Acebes,David Poza,Jose Manuel Gonzalez-Varona,Adolfo Lopez-Paredes
DOI: https://doi.org/10.1016/j.eng.2021.07.019
2024-05-31
Abstract:Earned duration management (EDM) is a methodology for project schedule management (PSM) that can be considered an alternative to earned value management (EVM). EDM provides an estimation of deviations in schedule and a final project duration estimation. There is a key difference between EDM and EVM: In EDM, the value of activities is expressed as work periods; whereas in EVM, value is expressed in terms of cost. In this paper, we present how EDM can be applied to monitor and control stochastic projects. To explain the methodology, we use a real case study with a project that presents a high level of uncertainty and activities with random durations. We analyze the usability of this approach according to the activities network topology and compare the EVM and earned schedule methodology (ESM) for PSM.
General Economics
What problem does this paper attempt to address?
The paper discusses how to handle uncertainty in project management, particularly by introducing the Earned Duration Management (EDM) method to improve project schedule monitoring and control. Unlike traditional Earned Value Management (EVM), EDM expresses the value of activities in terms of work duration rather than cost. The paper analyzes the application of EDM in monitoring random projects through a case study with high uncertainty and random durations. It also compares the performance of EVM and Earned Schedule Management (ESM) in projects with different network topologies. The authors propose a method that considers inherent stochastic uncertainty to enhance project control and accurate final duration prediction. Different algorithms such as Linear Discriminant Analysis (LDA), Decision Trees (CART), K-Nearest Neighbors (kNN), Support Vector Machines (SVM), and Random Forest (RF) are compared for classification and regression problems to assess project completion time and schedule delays. Overall, the paper aims to provide more accurate project control and prediction tools through EDM to deal with uncertainty in project execution.