Multi-skill resource-constrained project scheduling problem considering overlapping: fuzzy multi-objective programming approach to a case study
Fateme Zarei,Mehrdad Arashpour,Seyed-Ali Mirnezami,Reza Shahabi-Shahamiri,Mohammad Ghasemi,Fateme ZareiMehrdad ArashpourSeyed-Ali MirnezamiReza Shahabi-ShahamiriMohammad Ghasemia Department of Architecture,Maeda Girls College,Technical and Vocational University (TVU),Gorgan,Iranb Department of Civil Engineering,Monash University,Melbourne,Australiac Department of Industrial Engineering,Faculty of Engineering,Shahed University,Tehran,Irand Department of Industrial Engineering,College of Engineering,University of Tehran,Tehran,Iran
DOI: https://doi.org/10.1080/15623599.2023.2260696
2023-10-06
International Journal of Construction Management
Abstract:Resource-constrained project scheduling problem (RCPSP) is a broadly researched issue in the literature. The purpose of the classic form of the problem is scheduling a set of activities considering resource and precedence constraints for minimizing the project completion time. Companies mostly deal with the issue of properly assigning multi-skilled workforces and maintaining the needed skill levels while implementing projects. In this study, a novel MILP model with three objectives is presented to tackle multi-skill RCPSP (MS-RCPSP). This study concentrates on minimizing project makespan, minimizing resource costs as well as tardiness costs, and maximizing quality under uncertainty. However, the standard MS-RCPSP is not able to consider several practical engineering requirements owing to its narrow assumptions. Therefore, key assumptions including overlap between activities, tardiness penalties of activities and the rework duration concept for activities in this model are considered. Due to the complexity of the real world, interval valued fuzzy numbers are taken into account for some of the problem's parameters. The efficiency of the proposed mathematical framework is represented using both a real case study to construct a railway bridge with 34 activities and large-size problem instances from MMLIB (MM50 and MM100). Since this model is multi-objective, a new extended IVF-ABS approach is presented in this study. Finally, the proposed approach is compared with two methods, namely SO and ABS, from the literature.