Flood-aware Optimal Power Flow for Proactive Day-ahead Transmission Substation Hardening

Mohadese Movahednia,Amin Kargarian
DOI: https://doi.org/10.48550/arXiv.2201.03162
2022-01-10
Abstract:Power system components, particularly electrical substations, may be severely damaged due to flooding, resulting in prolonged power outages and resilience degradation. This problem is more severe in low-elevated regions such as Louisiana. Protective operational actions such as placing tiger dams around substations before flooding can reduce substation vulnerability, damage costs, and energy not supplied cost, thus enhancing power grid resilience. This paper proposes a stochastic mixed-integer programming model for protecting transmission substations one day before flood events using tiger dams. A flood-aware optimal power flow problem is formulated for transmission system operators with respect to the protected/unprotected status of substations. The formulated model aims to identify critical substations whose protection maximizes grid resilience. The output of the proposed model is a day-ahead crew team schedule for installing tiger dams on transmission substations. The effectiveness of the proposed model is evaluated on a 6-bus system, and promising results are obtained.
Optimization and Control,Systems and Control
What problem does this paper attempt to address?
The problem that this paper attempts to solve is to enhance the resilience of the power system by taking preventive measures before the occurrence of flood disasters, especially to protect transmission substations from flood damage. Specifically, the paper proposes a stochastic mixed - integer programming model, aiming to determine the optimal plan for installing flood - protection barriers (such as Huba) one day in advance to protect transmission substations. Through this method, the damage cost of substations can be reduced, the grid resilience can be improved, and the power - outage time and scope can be decreased. The main contributions of the paper include: 1. **Proposing a new optimization model**: This model takes into account the protection status of substations and determines which substations need to be protected before the flood arrives through optimized scheduling. 2. **Considering network connections and the interactions between substations**: Different from previous studies, the model in this paper not only considers the protection of a single substation, but also the network structure of the entire power grid. 3. **Verifying the effectiveness of the model through simulation**: The simulation results on the 6 - node system show that this method can significantly reduce the expected cost, power - outage time and scope. Through these measures, the paper provides an effective tool for power system operators to better protect power infrastructure during extreme weather events, reducing economic losses and social impacts.