Research on process parameter optimization of irregular coal face

Qinghai Li,Zijun Wang,Nan Liu,Haoran Zhang,Zhaoying Li
DOI: https://doi.org/10.1038/s41598-024-62517-x
IF: 4.6
2024-05-29
Scientific Reports
Abstract:Based on the engineering background of 1353 working face in Daizhuang Coalmine, the paper identifies three primary issues with the working face mining process: conventional pressure relief means are limited, risk of impact and the length of working face changes, It also proposes comprehensive control measures to improve the blasting roof cutting scheme, optimize mining speed and the location of the stopping line. The three improvement measures mentioned above are simulated numerically, and the effects of the drilling and blasting plan, mining speed, and stopping line location on stress distribution are determined. The results show that by implementing the three improvement measures, the stress variation interval can be efficiently controlled and the working face's production safety can be increased. Finally, it is determined that the 1353 working face of Daizhuang Coalmine adopts the pressure relief method of drilling on one side and cutting the roof 20 m deep on the other side, and the mining speed of the working face is 3 m/day and the length of the stopping line is 85 m. Based on the on-site monitoring results, the implementation of comprehensive treatment measures can effectively improve the surrounding rock state of 1353 working face, which has certain guiding significance for the mining of irregular working face.
multidisciplinary sciences
What problem does this paper attempt to address?
The paper attempts to address the following issues: 1. **Limited conventional pressure relief methods**: - Due to the boundary coal pillar on one side of the 1353 working face transportation roadway, according to the "Coal Mine Water Prevention and Control Regulations," a waterproof coal pillar must be left at the boundary of the adjacent mine, and it is strictly forbidden to excavate in various waterproof coal pillars. Therefore, it is impossible to drill pressure relief holes on the boundary coal pillar, which does not meet the anti-impact requirements. 2. **Impact risk**: - The hard sandstone above the 1353 working face has strong stability, making the roof difficult to collapse. However, when the roof's overhanging length reaches the maximum self-stabilizing value, the roof will fracture, causing a large area of roof collapse, resulting in strong impacts in the goaf, severely threatening the safety of the working face. Additionally, the coal pillar bears greater static and dynamic loads during mining, making it more susceptible to mining stress damage, thereby triggering rock bursts. 3. **Changes in working face length**: - Due to geological conditions, the length of the 1353 working face changes multiple times during advancement. As the working face width decreases, the strike fracture step increases, and the dip fracture step decreases, which can damage the integrity of the overlying roof structure. These areas are prone to high-energy mine tremors, increasing the risk of working face mining. To address the above issues, the paper proposes comprehensive control measures, including improving the blasting roof cutting scheme, optimizing the mining speed, and determining the stop line position. Numerical simulation methods were used to analyze the effects of these measures. It was ultimately determined that the 1353 working face would adopt a method of single-side drilling and cutting the roof 20 meters deep on the other side, with a mining speed of 3 meters/day and a stop line length of 85 meters. These measures can effectively improve the surrounding rock conditions of the 1353 working face and provide some guidance for mining complex irregular working faces.