Life Cycle Assessment of 20 MW Wind Farm in Libya

Abdelbari Elmariami,Wedad El-Osta,Yasser Nassar,Yusef Khalifa,Mohamed Elfleet
DOI: https://doi.org/10.3103/S0003701X22601557
2023-07-18
Applied Solar Energy (English translation of Geliotekhnika)
Abstract:Life cycle assessment (LCA) was undertaken for a proposed wind farm of ten Gamesa wind turbines with a 2 MW each. A 20 MW land-based wind turbine's lifetime primary energy consumption was found to be 56 GWh, compared to the 2082 GWh of electric energy it produces. Energy payback takes 6.3 months, has a payback ratio of 38, and an energy intensity of 0.0269 kWhprim/kWhprod. The emission of 8.83 g/kWhprod of CO 2 eq. The cost savings associated with CO 2 mitigation amount to 56 485 million, in which could be used to invest in wind farms development. The GHG avoided emission is 7.7 M ton. The energy consumed by manufacturing process accounted for 79.4%, recycling comes in second with 15.6%, then transportation with 4.6%. The CO 2 emissions of production phase of the wind turbine accounted for 63.35% of total CO 2 emissions, while recycling accounted for 33.15% and transportation for 3.5%, with negligible share of landfilling and operation and maintenance phases.
What problem does this paper attempt to address?