Long-hole raise blasting in a single shot: Assessment of void ratio and delay time based on experimental tests

Shyamal Chandrakar,P.S. Paul,C. Sawmliana
DOI: https://doi.org/10.1016/j.engstruct.2022.115272
IF: 5.582
2022-11-19
Engineering Structures
Abstract:Long-Hole Raising (LHR) is the prime excavation technique used for driving the vertical and steeply inclined raise structures in underground mining and civil construction projects. However, progress rate of raising is an important factor as it has enormous impact on cost and productivity. Therefore, to enhance the development rate of long raises under safe working conditions, several experimental LHR blasts in a single-shot have been conducted in the four underground metalliferous mines. This paper aimed to investigate the influence of void ratio (i.e. empty space) and delay time on the advancement of raises, considering fair and good quality of rock mass. In order to accomplish long raises, various parallel long-hole cut designs were executed in the first cut-section by varying void ratios ranging from 7.00 % to 36.50 %. Meanwhile, up to 25 m long raises were advanced effectively using one blast. As a result, it was found that amount of void ratio, and delay intervals between two adjacent blast-holes need to be increased adequately for longer length of raises (i.e. for higher degree of confinement factor). Subsequently, required void ratios and delay timing for the specific blast-holes length were assessed to succeed LHR blast in a single-shot. Regression analyses were carried out to establish the best-fitted model using residuals plot assumptions. Eventually, two empirical equations were derived between void ratio and blast-hole length, allowing for the fair and good quality of rock mass. Moreover, delay interval between adjacent blast-holes should be at least 22 times the blast-hole length for effective construction of long raises.
engineering, civil
What problem does this paper attempt to address?