Two-stage assembly flow-shop scheduling problem with non-identical assembly machines considering setup times

A. Mozdgir,S.M.T. Fatemi Ghomi,F. Jolai,J. Navaei
DOI: https://doi.org/10.1080/00207543.2012.756151
IF: 9.018
2013-06-01
International Journal of Production Research
Abstract:In this paper, we address the two stage assembly flow-shop problem with multiple non-identical assembly machines in stage two to minimise weighted sum of makespan and mean completion time. Also, sequence dependent setup times are considered for the first stage. This problem is a generalisation of previously proposed two stage assembly flow-shop problems (TSAFSP). In many real world industrial and production systems, there is more than one assembly machine to assemble job components. After extending a mathematical mixed-integer linear programming model to solve the problem, we use GAMS software. The TSAFSP has been known as NP-hard. Therefore, our more general problem is NP-hard too and so for large sized problems the right way to proceed is with the use of heuristic algorithms. So in this paper a hybrid VNS heuristic, which is a combination of the variable neighbourhood search (VNS) algorithm and a novel heuristic is developed and its solutions compared with solutions obtained by GAMS. Computational experiments reveal that the hybrid VNS heuristic performs much better than GAMS with respect to the percentage errors and run times.
engineering, manufacturing, industrial,operations research & management science
What problem does this paper attempt to address?