Optimization of the Concrete Delivery and Placement Process Using a Simulation

Juraj Talian
DOI: https://doi.org/10.2478/sjce-2013-0006
2013-06-01
Slovak Journal of Civil Engineering
Abstract:Abstract Integrated construction processes are stochastic systems. For these cases a computer simulation is used. This paper presents the design and construction of an integrated construction process, i.e., the production-transportation-consumption of fresh concrete. When creating a model in an Extend v4, modelling techniques and a general knowledge of construction are used. Data obtained from actual processes is used for the model parameters and input variables. The main contribution is a simulation model developed for the process for the optimization and selection of variants. This approach complements the heuristic methods of the assessment of construction processes and exact methods, where the decisive body will have the values of the individual decision-making criteria.