Risks management model integrating the Analysis mode and failure effects within the Last Planner System to improve the time of real estate construction projects

Dary Velasquez,Samuel Carhuamaca,Julio Farje
DOI: https://doi.org/10.1109/coniiti53815.2021.9619752
2021-09-29
Abstract:The real estate construction sector is one of the most important economic activities in the development of a country, over the years it has been a unit of measurement of economic well-being. However, due to inconveniences, such as variability and inherent dangers in constructions, delays are created giving the probability that the deadlines established in real estate projects will be breached, causing construction as an investment to become increasingly remote, from being the best option in the labor market. To understand these problems, a survey was carried out of 15 professionals in works belonging to Lima Top, determining that 46.7% of those surveyed consider that the finishing phase has a greater number of problems at the time of its execution, establishing that one of the main delay factors in construction projects is inadequate planning and a lack of risks management. In this sense, this study focuses on carrying out an adequate planning and risks management by integrating the Analysis Mode and failure Effects (AMFE) within the Last Planner System (LPS) at the Lookahead Planning level as a tool for risks management. In this way, it contributes by establishing a risks management framework in the planning of the LPS and an improvement in the criteria of the actions to be taken to reduce risks, improving the execution time of construction projects. The results obtained after the integration of these two tools in the Monte Umbroso 816 project, indicated an improvement in the operation design, showing zero problems with quality controls and an increase in the percentage of completed items, compared to a previous week analyzed without the incorporation of the AMFE.
What problem does this paper attempt to address?