No room for error: How digital techniques helped Gilbert-Ash build a theatre in the Foreign and Commonwealth Office courtyard

Paul McGeachy
DOI: https://doi.org/10.1080/20450249.2019.1696593
2019-10-02
Construction Research and Innovation
Abstract:The Mayhew Theatre is an innovative teaching and presentation space newly built in the courtyard of the Grade 1 listed Foreign and Commonwealth Office building in London. Its complex design and the site's restrictive logistics led contractor Gilbert-Ash to turn to state-of-the-art technology to ensure everything went to plan in its design and construction. This case study explains the construction challenges faced, and Gilbert-Ash's use of Point Clouds for object-oriented modelling, software, and 3D laser imaging, which in turned has changed how the company approaches its projects.
What problem does this paper attempt to address?