Underslung traveler form technology application on the supporting formwork main deck kendari bay cable stayed bridge project, Indonesia
Krishna Mochtar,Sugeng Prastyo
DOI: https://doi.org/10.54660/.ijmrge.2024.5.4.982-991
2024-01-01
International Journal of Multidisciplinary Research and Growth Evaluation
Abstract:The use of Underslung Traveler Form (UTF) technology for cast in situ main deck cable stayed bridges is one alternative method of implementing bridge construction. The aim of this paper is to analyze the tensile rod the construction cost components, and the productivity of the UTF segmental works in the Kendari Bay Cable Stayed Bridge Project, Indonesia. The methodology includes both literature study and also conducting the analysis and design of tensile rod of UTF in the Kendari Bay Cable Stayed Bridge Project, in terms of its calculation, construction costs components, and productivity. From the analysis, the tensile required rod strength of form traveler when casting per segment of deck bridge with 9 m length with concrete is safe and strong. The total cost of Form Traveler Investment Construction on the Kendari Bay Cable Stayed Bridge Project is USD 3,918,42 (1 USD=Rp 16,000), with the components cost percentage, including 32,15% for the UTF design, trial assembly, hydraulic system, and operations, 56,71% for Materials and fabrications works, 7,25% for transport/deliveries, and finally 3,89% for helper equipment rents. The results of the analysis of the productivity of bridge deck segment casting using the UTF as many as 37 Segments obtained the duration of 9 days per segment from the initial plan target of 13 days per segment. The application of Traveler Form Technology needs to be supported by site management, including: Effective and efficient worker shift arrangements as well as skills, competencies, workforce expertise, Arrangement of main work equipment, Work Method Innovation, Optimization of Work Implementation with a fast cycle of work time duration so as to reduce operational costs.