Novel Probabilistic Approach for Quantification of Cost-Overruns Risk and Determination of Primary Causes

Tianyu Liu,Shen Zhang,Xingyu Wang
DOI: https://doi.org/10.1155/2024/8893201
IF: 1.43
2024-01-20
Mathematical Problems in Engineering
Abstract:Cost management is a crucial component of construction project management, which assumes an increasingly critical role in modern large-scale projects. Ideally, cost management is achieved through a comparison between the current cost and the predetermined cost schedule. However, in real-world projects, it is often difficult to consistently obtain accurate costs for each cost item throughout the project life cycle and to predict the probability of various risk occurrences. To address this challenge, we propose a novel building information modeling- (BIM-) based algorithm to quantify the risk of cost overruns and cost deviation; and identify the primary causes without a detailed cost breakdown. The role of BIM in our approach is to automatically extract precise quantitative information that we can use to calculate the probability density function of the current cost and the expected total cost and eventually combine reliability analysis to provide the risk probability. The numerical experiment demonstrates that this algorithm can estimate the probability of cost overruns and cost deviation, and identify the primary cause of deviation. Additionally, the sensitivity requirements for cost management can be adjusted by adjusting the parameters, indicating its potential to meet multiple requirements in the different projects. The proposed algorithm provides a method for detecting the current risk of cost overruns and cost deviation, as well as identifying the primary cause of deviation, which is of potential value in the practical applications.
engineering, multidisciplinary,mathematics, interdisciplinary applications
What problem does this paper attempt to address?
The paper attempts to address the issues of quantifying cost overrun risks and identifying the main causes in cost management of construction projects. Specifically, the paper proposes a new probabilistic method based on 5D BIM (Building Information Modeling) to quantify cost overrun risks and cost deviations, and to identify the main causes of cost anomalies without requiring detailed cost breakdowns. ### The main research objectives include: 1. **Establishing the association between cost and design models**: Achieved without the need for detailed cost breakdowns. 2. **Establishing the relationship between current expected cost and total expected cost**: Related to the current time. 3. **Quantifying the risks of cost overrun and cost deviation**: Setting warning thresholds. 4. **Identifying the main causes of cost anomalies**: Able to identify the main causes when cost deviations occur. Through this method, researchers hope to help project managers monitor the cost status of projects more effectively and take preventive measures in a timely manner. Additionally, the method utilizes reliability analysis techniques, combined with on-site management and schedule data, to improve decision-making efficiency and comprehensibility.