DESIGN AND OPERATION EXPERIENCE OF THE FIRST PILOT 220t/h CIRCULATING FLUIDIZED BED BOILER WITH A WATER COOLED SQUARE CYCLONE
吕俊复,刘青,张建胜,岳光溪,沈解忠,唐国勇,苏小平,朱晓峰,赵爱国
DOI: https://doi.org/10.3321/j.issn:0258-8013.2003.08.036
2003-01-01
Abstract:Based on the success of 75 t/h and 130 t/h CFB boilers with water-cooled square cyclone , the first one 220 t/h went into commercial operation successfully by the end of 2001, at Weihai Cogeneration Plant, Shandong Province. This boiler is one of the largest capacities CFB boilers constructed with Chinese domestic technology. The operating experience is presented. Because of the nature of the water cooled cyclone and the full water membrane structure of the boiler wall, the boiler show a unique performance on the shorter start up time, the resistance on the shut down, the lower temperature of circulating ash and excellence availability, etc. The particle size of fly ash, circulating ash and bottom ash of this boiler is very similar with those of the CFB boilers with round cyclone of equivalent diameter and working on a similar coal. Its combustion efficiency is higher than expected. The pollutant emission of the boiler is not beyond the local strict emission standard. Its fuel flexibility, high load variation ratio, especially, the excellent reliability satisfied the client.