PV-EASY

Yulai Yuan,Guangwen Yang,Yongwei Wu,Weimin Zheng
DOI: https://doi.org/10.1145/1851476.1851505
2010-01-01
Abstract:As the most widely used parallel job scheduling strategy in production schedulers, EASY has achieved great success, not only because it can balance fairness and performance, but also because it is universally applicable to most HPC systems. However, unfairness still exists in EASY. For real workloads used in this work, our simulation shows that a blocked job can be delayed by later jobs for more than 90 hours. In addition, EASY cannot directly employ parallel job runtime prediction techniques, because this would lead to a serious situation called reservation violation.
What problem does this paper attempt to address?