The analysis on the spewing failure in the project taking lead pipe grouting to go through the fault

姜耀东,朱道建,李琦,赵毅鑫
DOI: https://doi.org/10.3969/j.issn.1673-3363.2005.03.002
2005-01-01
Abstract:The DongHuanTuo mine transportation roadway meets the fault in the excavation. It is the first time to take the grouting to the tunnel at depth. It needs high technique and excavated method. Drilling arises spewing because of the unstable of rock. This article adopts the numerical simulation to analyse the causation. It is considered from the two aspects of mechanic and displacement, then it can direct the local work.