Study on Cycle-time of Integrated System with Six Tanks in Treating Municipal Sewage

Chao ZHANG,Hong-bin XU,Xi-wu LU
DOI: https://doi.org/10.3969/j.issn.1671-1556.2005.03.017
2005-01-01
Abstract:In allusion to problems of low treatment proportion of dispersive sewage water and serious nitrogen and phosphorus pollution in our country, a new technology named Intellective Integrated Dephosphorization and Denitrification System with Six Tanks was invented. The principle and running mode of the technology was introduced and the influence of cycle-time-setting on contamination-removing was studied in this paper.In the conditions of SRT13 d and HRT13h, pilot-scale test indicated that the process realized the optimal performance when cycle-time was 16 h, and the outlet could meet the strictest requirements of the national standard.
What problem does this paper attempt to address?