The Effect of Risks on Supply Chain Schedule Estimation

Limin Xu,Chengjie Xu
DOI: https://doi.org/10.1061/9780784481080.021
2017-01-01
Abstract:With increasing complexity and uncertainty of supply chain, efficiency becomes an urgent topic. The lack of coordination and interaction between the upstream and downstream perplexes product managers. Both issues enlighten the importance of accurate schedule estimation. Without regarding delay time in the supply chain systematically, most scholars add the calculated delay time separately between each contractor, neglecting the interactions between delays. This paper provides a useful framework to have a comprehensive impression of the time-related risks and further apply a simulation model to estimate the timeline rationally. To illustrate the usefulness of the framework, Scarborough subway extension project is analyzed. The result shows high adaption to the real case.
What problem does this paper attempt to address?