Research on the Smooth Blasting Influenced by the Cave Cutting Method

Ke MAN,Xiao-li LIU,Xi-yong WANG,Zhen-ming CHEN,Liang CHEN,Ju WANG
DOI: https://doi.org/10.3969/j.issn.1671-1815.2017.19.015
2017-01-01
Abstract:Based on the smooth blasting method,the blasting parameters of the Beishan Excavation Tunnel have been designed,which is much more suitable to this project.Furthermore,the smooth blasting influenced by the cave cutting method has been researched in detail.Three different cutting methods have been designed,i.e.parallel hole cutting,single wedge hole cutting and duplex wedge hole cutting,for the same rock mass and geological condition with the same detonator and explosive.In advance,the blasting has been carried out under different cutting methods.It is found that the parallel cutting has shown a better smooth effect,and the single and duplex wedge cutting has indicated that the size of the rock fragment is almost even and the throw distance of the rock is a bit suitable for slag.It should be noticed that,blasting method includes numerous blasting parameters,which interaction each other.Those blasting parameters obtained just on the cutting method,and the result and the theoretical knowledge could be applied to the blasting and excavation of the deep geo-engineering and the HLW geo-disposal.
What problem does this paper attempt to address?