Construction and Operation of Pilot Project for Treatment of Tannery Wastewater

Qiu-shi WANG,Jun WU,Xuan ZHANG,Zhen-peng CHEN,Bing-cai PAN
DOI: https://doi.org/10.19853/j.zgjsps.1000-4602.2014.23.011
2014-01-01
Abstract:Tannery wastewater is characterized by high concentration of NH3- N and sulfate,poor biodegradability and large variations in wastewater quantity and quality. Conventional treatment processes are often difficult to ensure the effluent NH3- N and COD meet the discharge standards. A pilot project for treatment of tannery wastewater was constructed by combining hydrolytic acidification,up-flow anoxic humus filter and SBR. The pilot project was equipped with on-line monitoring and an automatic control system. The capacity of the pilot project was 24 m3/ d. S2-,SO2-4,COD and NH3- N could be effectively removed from tannery wastewater with the effluent concentration of COD lower than 100 mg / L and NH3- N lower than 15 mg / L,meeting the national first class discharge criteria.
What problem does this paper attempt to address?