Study on failure and deformation of surrounding rock under high tectonic stress during construction of underground cavern group for hydropower station

SHENG Songtao,ZHANG Feilian,LI Jinshan
2014-01-01
Abstract:Aiming at the failure of the rock mass during the construction of the underground cavern group for Houziyan Hydropower Station, the mode of the deformation and failure of the surrounding rock therein is studied, and then the genesis mechanism of the stress driving deformation under the high tectonic stress is analyzed with Mohr circle of stress and the composite strength criterion concerned, furthermore, the effective engineering countermeasures are proposed as well. The study achievements are favorable to further understand the stability of the deformation of the surrounding rock under high tectonic stress, thus can provide some references for the design and construction of the similar cavern group for underground powerhouse.