Numerical Analysis and Field Monitoring on Deformation of the Semi-Top-Down Excavation in Shanghai
Zhong-hui Huang,Xiang-shan Zhao,Jin-jian Chen,Jian-hua Wang
DOI: https://doi.org/10.1061/9780784413456.021
2014-01-01
Abstract:A semi-top-down excavation method is proposed for construction of an underground metro station in Shanghai, which is close to an elevated metro station and several high-rise buildings with shallow foundations. The semi-top-down method combined the construction sequence of temporary strut and middle floor slab of the substructure during excavation, which united advantages of the top-down method and the bottom-up method. The efficiency of the new method to reduce the environment deformation is analyzed based on the numerical analysis and field measurements. Both the settlement of buildings and the lateral displacement of retaining structure were obtained numerically and compared with those of the traditional excavation method. Predicted results shows that the increase of building settlements trend to be mild after the middle slab is constructed, which means that the semi-top-down method has a good effect on controlling the surrounding deformation. The monitoring results show that the proposed series of techniques is effective and the displacements of the adjacent structures are similar to that predicted by numerical method. The settlement observation of the high-rise building and elevated metro station show that both the settlements and the differential settlement are within control. Therefore, the new method can ensure the efficiency of deep excavation and reduce the environment deformation.
What problem does this paper attempt to address?