Abstract:In recent years, photovoltaic power generation and greenhouse planting (PPG&GP) have become effective approaches for reconstructing and restoring the ecological environment of old coal-mining industry bases, such as Xintai City. However, the ecological impacts or improvements of the PPG&GP projects and their daily operations on the local environment are still unclear. To solve these problems, this study retrieved the ground deformation velocities and time series of the study region by performing the Small-Baseline Subset (SBAS)-Interferometric Synthetic Aperture Radar (InSAR) technique on the Advanced Land Observing Satellite (ALOS) PALSAR and Sentinel-1 SAR datasets. With these deformation results, the spatial analysis indicated that the area of the subsidence region within the PPG&GP projects reached 10.70 km2, with a magnitude of approximately −21.61 ± 12.10 mm/yr. Also, even though the ground deformations and their temporal changes were both visible in the construction and operation stages of the PPG&GP projects, the temporal analysis demonstrated that most observation points finally entered into the stationary phases in the late stage of the observation period. This phenomenon validated the effectiveness of the PPG&GP projects in enhancing the ground surface stability in coal-mining areas. Additionally, the precipitation, geological structure, increased coal-mining depths, and emergent agricultural modes were assumed to be the major impact factors controlling the ground deformation within the local PPG&GP projects. Finally, a novel risk assessment method with a designed index of IRA was utilized to classify the ground subsidence risks of the PPG&GP projects into three levels: Low (69.7%), Medium (16.9%), and High (9.4%). This study sheds a bright light on the ecological monitoring and risk management of the burgeoning industrial and agricultural infrastructures, such as the PPG&GP projects, constructed upon the traditional coal-mining areas in China from a multi-temporal InSAR perspective.
environmental sciences,imaging science & photographic technology,remote sensing,geosciences, multidisciplinary
What problem does this paper attempt to address?
### Problems Addressed by the Paper This paper aims to study the surface subsidence, driving factors, and risk assessment of the photovoltaic power station and greenhouse planting (PPG&GP) project located in the coal mining subsidence area of Xintai City, Shandong Province, China. Specifically: 1. **Surface Subsidence Monitoring**: - Using Small Baseline Subset (SBAS) Interferometric Synthetic Aperture Radar (InSAR) technology, combined with Advanced Land Observing Satellite (ALOS) PALSAR and Sentinel-1 SAR datasets, to obtain surface deformation velocity and time series in the study area. - The analysis results show that the subsidence area within the PPG&GP project area reaches 10.70 square kilometers, with an average subsidence rate of approximately -21.61 ± 12.10 mm/year. 2. **Ecological Impact Assessment**: - Although surface deformation and its temporal changes were observed during the construction and operation phases of the PPG&GP project, most observation points eventually entered a stable stage, verifying the effectiveness of the PPG&GP project in improving the surface stability of the coal mining subsidence area. 3. **Driving Factors Analysis**: - The study hypothesizes that precipitation, geological structure, increased coal mining depth, and emerging agricultural models are the main factors controlling ground deformation within the local PPG&GP project. 4. **Risk Assessment**: - A new risk assessment method is proposed, and an index named IRA is designed, categorizing the surface subsidence risk of the PPG&GP project into three levels: low risk (69.7%), medium risk (16.9%), and high risk (9.4%). Through the above research, this paper provides a new perspective on ecological monitoring and risk management for industrial and agricultural infrastructure construction in traditional coal mining subsidence areas.